AVA Architects completes the topping-out of the WATEC Building project in just 3 months, ahead of schedule while ensuring quality and safety. The project promises to become a unique architectural landmark at FPT Complex Da Nang.
AVA Architects, together with the investor and partners, recently held the topping-out ceremony for the WATEC Building project, marking an important milestone in the construction process. With a rapid construction pace of just 3 months, the project has completed the structural phase, demonstrating the seamless collaboration among parties and the relentless efforts of the team.
In just 3 short months, the WATEC Building has completed 1 basement, 6 above-ground floors, and 1 technical floor, surpassing the anticipated schedule while absolutely ensuring quality standards and labor safety. This impressive achievement is attributed to the harmonious coordination between AVA Architects’ design and construction teams, the tireless efforts of engineers and workers, and the dedicated support from the investor.
The WATEC Building is not just an ordinary office structure but also a unique architectural symbol, affirming AVA Architects’ position at FPT Complex Da Nang. The project promises to become a prominent highlight, providing an ideal working space for users and contributing to the area’s development.
AVA Architects sincerely thanks the investor and all personnel who contributed to the project’s success, helping the WATEC Building achieve this significant milestone and move into the overall completion phase.
Project Information:
-
Project Name: Office WATEC Building
-
Land Area: 240m²
-
Number of Floors: 1 basement, 6 above-ground floors, 1 technical floor
-
Total Construction Floor Area: 1,460m²
-
Commencement Date: 08/2024
-
Expected Completion: 08/2025
In conclusion, the successful topping-out of the WATEC Building project is a testament to AVA Architects’ outstanding construction capabilities, professionalism, and spirit of cooperation. We are committed to continuing our efforts to complete the project on schedule and deliver the best value to our clients.

Recruitment06/03/2025AVA Architects Recruitment Q1-2025
News about AVA06/03/2025Kickstarting 2025: AVA Architects Signs Design Contract with AnhDuyen Audio
News about AVA06/03/2025AVA Apartment Successfully Topped Out: A New Milestone in the Journey of Creating Value
News about AVA06/03/2025WATEC Building Topped Out at Lightning Speed: A 3-Month Journey to a Significant Milestone